1.3 Sustainability as a performance target
2m 33s
Andy Murray, while discussing the PRINCE2 V7 project management guidance, elucidates the concept of setting performance targets and managing them effectively. PRINCE2 recommends the use of tolerances, offering a margin for flexibility in project controls. This prevents managers from overreacting to minor deviations from a plan. The idea is to establish performance benchmarks, monitor progress against them regularly, and adjust accordingly. Using metaphors, Murray likens this to strategically landing on a specific lily pad or correctly aligning with a designated section of a runway during a plane's descent. This approach ensures the project aligns with its desired outcomes despite inevitable variations.