Brad Bigelow

Brad Bigelow

Project and program management, system acquisition, and network operations.

Specialties: Cyber defence, cyberspace operations, IT operations, program and project management, international contracting, PRINCE2, MSP, PMP

Linkedin profile

Watch Trailer Share
Brad Bigelow
  • Work breakdown structure

    Brad Bigelow, a PRINCE2 V7 Author, discusses the importance of integrating both Product Breakdown Structures (PBS) and Work Breakdown Structures (WBS) in project management. He argues that solely relying on one of these tools is a mistake, as most projects involve both work and materials (outputs...

  • Issues and changes to the baseline

    Brad Bigelow, a PRINCE2 V7 author, emphasizes the crucial distinction in project management between issues and changes. According to him, it's essential to understand that issues are common occurrences in any project and are distinct from changes, which refer to modifications to the project basel...

  • Misinformation within projects, issues or change?

    Brad Bigelow, a PRINCE2 V7 Author, highlights the unique position of project managers (PMs) in organizational projects, especially in the context of stakeholder management and communication. He notes that often, the project manager may be the only constant figure in a project, particularly in lon...

  • Operations vs projects

    Brad Bigelow, a PRINCE2 V7 Author, provides insightful commentary on the nature of project management in contrast to ongoing operations. He emphasizes that project management is a technique used to deliver finite packages of change within organizations, characterized by a distinct beginning, midd...

  • PMBOK and PRINCE2

    Brad Bigelow, an author of PRINCE2 V7, discusses the relationship between PRINCE2 and the PMI’s PMBOK (Project Management Body of Knowledge), emphasizing that they are often mistakenly seen as competing disciplines. He clarifies that PRINCE2 is a well-established methodology, refined through thou...

  • Tolerances

    Brad Bigelow, a PRINCE2 V7 author, emphasizes the importance of tolerances in the PRINCE2 project management framework, describing them as one of its "secret sauce ingredients." He explains that tolerances provide a control mechanism that empowers project managers (PMs) to make tactical decisions...

  • Iron triangle; time, scope and cost

    Brad Bigelow, a PRINCE2 V7 author, discusses the fundamental aspects of project management, particularly focusing on the interrelationship of time, scope, and cost, often referred to as the iron triangle in project management. He emphasizes the crucial trade-offs that project managers must consid...

  • Planning documentation does not mean successful delivery

    Brad Bigelow, an author of PRINCE2 V7, discusses the role of documentation in project management. He emphasizes that documentation serves as a tool to establish a social contract, outlining key project aspects such as objectives, participants, duration, and cost. Bigelow highlights the importance...

  • Full interview with Brad Bigalow and Scott PRINCE2 V7 plan, quality & issues

    In an interview conducted by Scott Spence with Brad Bigelow, a key author of PRINCE2 V7, various updates and insights into the latest version of PRINCE2 were discussed. Bigelow was approached to contribute to the new PRINCE2 guide due to his extensive experience in project management, including h...